Sunday, April 27, 2014

Footings and Frost Wall - April 2014

The first challenge of building the house was the footings.  The basis of every house start with the footings, and we wanted to make sure everything was done perfectly.  Of course, when its your first time doing house footings, that is a big undertaking, but research had been done, and we had advice  from other builders to help guide the process.  One of the most important steps was making sure the footings were at the correct height and that everything was level.  We used a transit and sight to get everything just right.    

Footings before pouring concrete

We used 2x12" boards and 2x10" boards for the footing forms.  There were also two places where the footings had to be stepped down, which can be seen in the photos below.  Rebar needed to be cut, bent and placed into the footings, and then tied together.  Rebar is basically steel rods that are added to provide strength to the concrete.  The size and placement of the rebar is dependent on the house plans, and the building code.





Tying rebar in the footings
We were ready for the first concrete pour for the footings.  Unfortunately, as soon as the concrete truck pulled in, it started to rain!  One of the steps needed extra bracing during the pour, so that was intense, but both Dad's were there to help, and the job was completed without loosing too much concrete.  The second pour for the frost wall went without a hitch (pictured below)!

Waiting for concrete for the frost wall 



Footings after being poured


Once the footings were poured, we were ready for our first order of Fox Blocks, the ICF materials that we will be using to build the house.  The blocks arrived and the frost wall was built.

First trailer of Fox Blocks!

View of the frost wall before being poured


Securing large joints with scabs of plywood


Frost wall and footings for the lally columns ready to be poured


Tuesday, April 15, 2014

Breaking Ground - April 2014


We finished prepping the site at the end of March.  We had removed all the stumps and visible large rocks on the site.  The house was staked out by the engineer, and we were ready to break ground!



Panoramic of the cleared building site
When all the stumps and rocks were removed we started digging our foundation. The first day was only a few hours in the afternoon but we made progress quickly and we were able to move around 550 yards of dirt from where our house was going. Thanks to Uncle Mike and Katie's Dad we had 2 more machines to help our backhoe dig the hole.

Breaking Ground, April 3, 2014!

The hole at the end of Day 1
The digging machine line up!  Mini-Ex, Kubota and Caterpillar!






Excavation of the house completed!  
Happy Tiller!